# Week Tasks Status Comments
00 2011-04-21 - 2011-04-24 Outline
Setup git repo and SVN sync
Setup initial TeX files
Setup HTML page for status updates
100%
100%
100%
100%
01 2011-04-25 - 2011-05-01 Reconstruct old study thesis setup
Write test suite for lowpan
100%
100%
02 2011-05-02 - 2011-05-08 Write test suite for DTN
Verify old evaluation with new tests
Write section about hardware
100%
100%
100%
Milestone 1 (Verified state on top of the old work, test suite)
03 2011-05-09 - 2011-05-15 Get related work papers
Fill in paper in BibTeX
Start related work section in thesis
100%
100%
100%
04 2011-05-16 - 2011-05-22 Port lowpan-tools to libnl2 (optional)
Port IBR-DTN to libnl2 (optional)
Setup for cross compilation
Write about other then IP CLs
0%
0%
100%
100%
05 2011-05-23 - 2011-05-29 Update kernel
Fix kernel bug in cc2420
Run test suite without 100ms hack
Add FCS check
Try hw address translation
Try if auto ACK is working
Run test suite
Write section about improvements
100%
80%
100%
100%
100%
100%
100%
100%
Milestone 2 (Fixed lower layer for speed improvements)
06 2011-05-30 - 2011-06-05 Add compressed bundle header to CL
Buy BEN-WPAN dongles
Write about compressed header
100%
100%
100%
07 2011-06-06 - 2011-06-12 Add segmentation to CL 100%
08 2011-06-13 - 2011-06-19 Add segmentation to CL
Write about segmentation
100%
100%
Milestone 3 (Convergence layer enhancements)
09 2011-06-20 - 2011-06-26 Test discovery with Georgs work 10%
10 2011-06-27 - 2011-07-03 Run the nodes without coordinator
Receive bundles from Georgs nodes
Write about contiki compat work
100%
20%
100%
Milestone 4 (Contiki compatibility work)
11 2011-07-04 - 2011-07-10 Get the usb wifi dongle working
Use SD card for bundles
Route DTN bundles to wifi and back
50%
0%
0%
12 2011-07-11 - 2011-07-17 Use BEN-WPAN to run DTN on laptop
Test compatibility between devices
100%
100%
13 2011-07-18 - 2011-07-24 Show case with mine and Georgs work
Half term presentation
0%
100%
Milestone 5 (General work done, presentation)
14 2011-07-25 - 2011-07-31 Write about presentation setup
Evaluate AUTO ACK options
Implement AUTO ACK in ieee802154
0%
100%
100%
15 2011-08-01 - 2011-08-07 Implement AUTO ACK in ieee802154
NACK bundles in IBR-DTN if no space
100%
0%
16 2011-08-08 - 2011-08-14 Vacation 100%
17 2011-08-15 - 2011-08-21 Test different strategies re-submit 0% Milestone 6 (Re-submit research)
18 2011-08-22 - 2011-08-28 Pin down throughput bottlenecks
Evaluation
100%
100%
19 2011-08-29 - 2011-09-04 Evaluation 30% Milestone 7 (Evaluation)
20 2011-09-05 - 2011-09-11 Write thesis 100%
21 2011-09-12 - 2011-09-18 Write thesis
Review
0%
0%
22 2011-09-19 - 2011-09-25 Work review in 0%
23 2011-09-26 - 2011-10-02 Write thesis
Review
0%
0%
24 2011-10-03 - 2011-10-09 Work review in 0%
25 2011-10-10 - 2011-10-16 Write thesis 0%
26 2011-10-17 - 2011-10-20 Print and bind thesis 0%
XX 2011-11-XX Final presentation 0%